ATTENTION: Please be advised that depending on your location and the type of service required, it can take several weeks to complete the construction and connection of electrical service. We appreciate your patience and understanding as we work with you to make this process as smooth as possible. 

 

To connect power to a non-permanent or low usage structure (barns, shops, etc.), you will need:

  • To have a copy of your warranty deed available to attach to the membership application.

  • To complete the membership application

 

To connect power for oil & gas pumping and/or pipeline usage:

  • Complete the membership application

  • Note: The Customer shall pay in advance as a non-refundable aid in construction 100% of the actual cost of all construction.

 

To connect power for temporary line extensions (construction sites, firework stands, etc.):

  • Complete the membership application

  • Note: The Customer shall pay in advance as a non-refundable aid in construction 100% of the actual cost of all construction plus the cost of removal, less the salvage value of the transformer.

 

To connect power to subdivision developments and mobile home parks:

  • Review Policy C-14 Section D and adhere to all requirements therein

  • Complete the membership application

 

Additional documentation that may be required:

 

To start the process, you will need to:

  • Call East Central at 918-756-0833 and talk with one of our helpful customer service representatives about your new construction. Our representatives will walk you through the application process, set up your account, discuss any fees associated with the account, and get your information to a field representative who will contact you for next steps. A field representative should contact you within three business days of the initial call. 

  • Our field representative will arrange to meet with you at the service location to determine the meter location, line route, service capacity, and other construction details. Please have your site plan and electrical load requirements with you at this meeting. The representative will also provide you with easement forms, membership documents, and other information that must be completed before construction can begin.

  • Please return all payments, forms, easements, permits, and other documents as requested by East Central. After the field representative has completed the construction drawings and received your documents, your new service will be scheduled for constructions.

 

Please be aware, connecting power to commercial and industrial new construction, including typically takes around six to eight weeks to complete.

 

If you have any questions or concerns throughout this process, please give us a call at 918-756-0833.